Project :

Supply and lay oil line of dia.6'‘ & 8'' of carbon steel pipe and 250 mm of vitrified clay pipe in the area of tank farm.

Contract:

N° 01/2009

Duration:

9 Months

Scope of Work:

  • Supply of 1950 LM of CS pipe size 6”
  • Supply of 1450 LM of CS pipe size 8”
  • Application of external coating for CS pipes
  • Excavation and removal of deteriorated CS oil lines
  • Construction & Laying of concrete pits
  • Laying of new CS sewer lines & connection with pits
  • Hydro-testing of all lines
  • Supply of 250 Vitrified clay pipe size 250 MM
  • Excavation and removal of deteriorated sewer lines
  • Laying of new VC sewer lines & connection with pits
  • Hydro-testing of all lines

Project :

Ethylene Dichloride Unloading & Caustic Soda Loading Facilities Project Remaining Works

Contract:

N° 01/2010

Duration:

6 Months

Scope of Work:

  • Painting of Carbon Steel pipes size 8” & 4”:
    • :: 1200 LM EDC 8” pipeline in the Jetty
    • :: 2200 LM EDC 8” pipeline from tank farm
    • :: 1000 LM NAOH 8” pipeline from tank farm
    • :: 1500 LM Auxiliary 4” pipes from tank farm
  • Supply and installation of insulation materials for 8” NAOH pipeline of 1000 LM length
  • Supply and installation of Galvanized Carbon Steel pipes, fittings and accessories for fire fighting system to be installed in EDC tank zone
  • Supply and installation of No. 2 electrical actuators necessary for No. 2 Three way valves size 8”